Shingle Transfer
Start 06-10-08
One Week
Recharge
Start 04-10-08
One Week
Reprofiling
Start 11-09-08
All Winter
Winter Works
Completed
07-04-08
Storm Damage
Repair started
10-03-08
Recycling
Completed
28-01-08
Recycling
Start 14-01-08
Two Weeks
Shingle Transfer
Start 07-01-08
One Week
Recycling
Completed
24-10-07
Recycling
Start 08-10-07
Three weeks
Shingle Transfer
Start 01-10-07
One week